Perrys Lane Culvert: update

Perrys Lane Culvert: update

Councillor Cathy Martyn Update:
Works to reinstate the culvert roof were intended to be completed by mid-September. Unfortunately further delays have been encountered due to product availability with the suppliers – this has resulted in long lead times to get the required items. They are not expecting delivery until the first week of November which should mean that works should be completed sometime towards the end of November.
Cathy