Communication from Cathy Martyn – Perrys Lane culvert update

Communication from Cathy Martyn – Perrys Lane culvert update

Works started yesterday to finish the work on Perrys Lane culvert. The outline programme is:
w/c 16/08/21 – break out roof
w/c 23/08/21 – culvert clearance (SBC Environment Team and EA)
w/c 30/08/21 – install formwork, rebar etc. and pour new culvert roof
w/c 06/09/21 – new roof cures, pavement tarmac, new shingle to driveway
w/c 13/09/21 – driveway operational (subject to curing time of new concrete)
If you have any queries, please email me or one of your other 2 borough councillors. Our contact details are as follows: